We offer a “12 Week – LOWEST BUILD TIME” on single story homes
There are 5 Stages of construction when building a house – Base, Frame, Enclosed, Fixing and Practical Completion.
All of these stages on an OJ Pippin Homes single storey home will be built within 12 weeks of receiving council approval.
Just days of receiving council approval the slab will go down then watch as the walls come up, the tiles go down and as the bathroom and kitchen are fitted via weekly update photos emailed to you.
Week 1
BASE – watch the slab go down.
Week 2
Frame
Week 3
Roofing
Week 4
Plaster board
Week 5
ENCLOSED – watch the windows, doors and roof go on.
Week 6
Carpentry and waterproofing
Week 7
Painting and driveway
Week 8
FIXING – kitchen and bathroom get fitted.
Week 9
Builder site clean
Week 10
Tiling & Landscaping
Week 11
Tiling and carpets
Week 12
PRACTICAL COMPLETION – enjoy your home.