A Beautiful Two Storey Home at Bald Hills

progress

Over the building period of this home we’ll be updating progress photos so you can view each stage of the construction process of this house.

Selected from the OJ Pippin Homes standard floorplan designs, the Cooper 270 two storey home design facade is splendid looking house and a flows beautifully through-out.

Before OJ Pippin homes start building on a site a Preliminary site inspection of the proposed land development is essential to attend a good understanding of the scope of work required and that there is no costly surprises when the build starts. if you would like to read more about hidden costs of building go to HIDDEN COSTS articles: Click here

Stage 1 – After the site is cleared, the trenches for the under slab pluming is positioned. The next stage is the footings and concrete slab to be poured.

Stage 2 -The lower house frame has been erected and the second storey is going up.

Stage 3 – The roof trusses have been mounted and the lower section is currently being bricked.  Further carpentry is undertaken on the house for internal fixtures.

Stage 4 –  The roof is now installed and the all the glass components are now secured into position.

Stage 5 – External bricking is now complete and the plasterboard has been installed throughout.  Now that the scaffolding is installed the carpenters can start on the cladding on the upper level.

Stage 6 – Carpenters have now completed the external cladding on the upper level. Inside a lot is happening, the waterproof is done and the tilers are preparing the floors. Plasters have mounted the cornices. Cabinetry has arrived for the kitchen installation.

Stage 7 – Outside this house is really starting to take shape with the rendering and painting almost completed. The tilers have now finished and all the cabinetry has been installed in the kitchen and bathrooms.

Stage 8 – Inside now that the internal painting finishing touches are happening so all the fit offs can been scheduled for plumbing, wardrobes, Blinds, electrical and air-conditioning. Outside the aggregate driveway has been laid.

Stage 9 – The finishing touches are now happening occurring: landscaping undertaken, blinds fitted, vanity basin and tops installed, the next step is for the carpet laid.

Stage 10 – Defect check has been completed and any small imperfections have been rectified before handover to the client.  After the final clean the professional photographer takes before the handover – This beautiful home is now ready for client to move into their new home.